What Is an Earned Value Performance Analysis Template and How Does a Project Manager Use It?
A An Earned Value Performance Analysis (EVPA) Template is a project management tool that helps track project performance by comparing planned progress, actual costs, and earned value. It provides key insights into whether a project is on track, over budget, or behind schedule, allowing project managers to make data-driven decisions.
Why Use an Earned Value Performance Analysis Template?
- Tracks project performance in real-time
- Identifies budget overruns and schedule delays early
- Provides objective data for forecasting project outcomes
- Supports proactive decision-making and risk management
How to Use an Earned Value Performance Analysis Template
- Gather Key Project Data
Before using the template, collect the following:- Planned Value (PV): The budgeted cost of work scheduled at a specific point in time.
- Earned Value (EV): The budgeted cost of actual work completed.
- Actual Cost (AC): The actual cost incurred for the work completed.
- Enter Data into the Template
Input PV, EV, and AC into the EVPA template to calculate performance metrics: - Schedule Performance Index (SPI) = EV ÷ PV (SPI >1 means ahead of schedule; SPI <1 means behind)
- Cost Performance Index (CPI) = EV ÷ AC (CPI >1 means under budget; CPI <1 means over budget)
- Schedule Variance (SV) = EV - PV (Positive SV = ahead of schedule; Negative SV = behind)
- Cost Variance (CV) = EV - AC (Positive CV = under budget; Negative CV = over budget)
- Analyze Performance Trends
Review SPI and CPI trends to determine whether the project is on track. A CPI or SPI below 1 signals a need for corrective action. - Forecast Project Completion
Use Estimate at Completion (EAC) and Estimate to Complete (ETC) calculations to predict final project costs and completion dates. - Take Corrective Actions If cost or schedule variances are significant, adjust resources, timelines, or scope to realign the project with its goals.
Final Thoughts
An Earned Value Performance Analysis Template is a powerful tool for maintaining project control. By tracking key performance metrics, project managers can make informed decisions, prevent budget overruns, and keep projects on schedule.
Want to enhance project tracking? Download CEG’s Earned Value Performance Analysis Template today!




- ©2025 Corporate Education Group, operated by CEG Operating Company, LLC. All Rights Reserved.
Privacy Policy | Terms and Conditions - PMI®, PMP®, CAPM®, PgMP®, PMBOK®; and the PMI®; Registered Education Provider logo are registered trademarks of the Project Management Institute, Inc. CBAP® and IIBA® are registered trademarks of International Institute of Business Analysis. All other trademarks mentioned on this site are property of their respective owners. All rights reserved. CEG is an approved Authorized Partner within the Blanchard Authorized Partner Program and is licensed to market, sell, and train SLII®.